Thanks to a huge effort from the team today, where the Yareen Road Level Crossing has now been reactivated. Check out this quick snapshot of our volunteers at work following by the exciting sound of bells with flashing lights.
Today, the team were able to complete:
🔹 Removal of vegetation around the approaches
🔹 Painting of the control hut
🔹 Repairs to the roof of the control hut
🔹 Repairs to damaged wiring in the bell circuits
🔹 Painting of fences
🔹 Painting of light and bell housing
🔹 Re-install warning signs
🔹 Install new Railway Crossing signs
🔹 Testing of lights, bells and driver indicator light
P.S. UGL Regional Linx will be back shortly to re-cut the flange gaps in the new asphalt after recent resurfacing works.
This will allow our track machines to travel through this section of line so that we can complete further vegetation control through the railway corridor and continue our track repairs.